Defendants Yolo County and its board of supervisors (collectively, the County) adopted a revised mitigated negative declaration and issued a conditional use permit to real parties in interest to operate a bed and breakfast and commercial event facility supported by onsite crop production intended to provide visitors with an education in agricultural operations (project). A trial court found merit in three of several arguments presented to challenge the decision, specifically finding substantial evidence supported a fair argument under the California Environmental Quality Act that the project may have had a significant impact on the tricolored blackbird, the valley elderberry longhorn beetle (beetle), and the golden eagle. The trial court ordered the County to prepare an environmental impact report limited to addressing only the project’s impacts on those three species. Further, the Court ordered the project approval and related mitigation measures would remain in effect, and the project could continue to operate. Plaintiffs-appellants Farmland Protection Alliance and Yolo County Farm Bureau appealed, contending the trial court violated the Act by: (1) ordering the preparation of a limited environmental impact report, rather than a full one, despite finding substantial evidence with respect to the three species; (2) finding the fair argument test was not met as to agricultural resource impacts; and (3) allowing the project to continue to operate during the period of further environmental review. Real parties in interest cross-appealed, arguing the trial court erred in finding substantial evidence supported the significant impacts on the three species. They requested an order vacating the judgment requiring the preparation of the limited environmental impact report (even though the limited environmental impact report was already certified by the County). The Court of Appeal concluded Public Resources Code section 21168.9 did not authorize a trial court to split a project’s environmental review across two types of environmental review documents. The trial court thus erred in ordering the County to prepare a limited environmental impact report after finding the fair argument test had been met as to the three species. In the unpublished portion of the opinion, the Court concluded the trial court did not err in: (1) upholding the County’s determination that the project was consistent with the Code and the Williamson Act; and (2) finding substantial evidence supported the projects effects on the beetle. Judgment was reversed requiring the preparation of a limited impact report, and the case remanded with directions to issue a peremptory writ of mandate directing the County to set aside its decision to adopt the revised mitigated negative declaration and to prepare a full environmental impact report for the project. View "Farmland Protection Alliance v. County of Yolo" on Justia Law

by
Respondent City of Tustin (City) reviewed a proposed construction of a new gas station and ancillary facility (project) pursuant to the California Environmental Quality Act, Public Resources Code section 21000 et seq. (CEQA), and concluded the project was exempt from CEQA under the categorical exemption for “in-fill development.” After the City approved the project and filed a notice of exemption, appellant Protect Tustin Ranch (Protect) sought a writ of mandate to set aside the City’s approvals due to what it claimed was an erroneous finding by the City that the project was exempt from CEQA. The trial court denied Protect’s petition. The Court of Appeal found no error and affirmed the judgment. View "Protect Tustin Ranch v. City of Tustin" on Justia Law

by
The University of California (Regents) approved a new development for additional academic space and campus housing, certified a final supplemental environmental impact report (SEIR), then filed a notice of determination regarding the project, which identified ACC as the developer and CHF as the ground lessee and borrower in connection with the housing. SBN challenged the certification of the SEIR under the California Environmental Quality Act (CEQA), citing various omissions. A first amended petition, substantively identical to the initial petition, added ACC and CHF as real parties in interest, Public Resources Code 21167.6.5(a)). SBN subsequently filed a first amendment to that petition, seeking to add ACC’s parent companies (jointly, ACC) as real parties in interest.ACC and CHF argued SBN failed to name them as parties within the applicable limitations period. The court of appeal affirmed the dismissal of ACC and CHF, citing Code of Civil Procedure 389(b). The courts declined to dismiss the entire petition. SBN would have no way to challenge the SEIR if the case was dismissed, whereas ACC and CHF were parties in a related case challenging the same SEIR and unlikely to be subject to a harmful settlement. The court concluded ACC and CHF were not indispensable parties, noting the unity of interest between those parties and the Regents. View "Save Berkeley's Neighborhoods v. Regents of the University of California" on Justia Law

by
Ordinances banning “land uses in support of” new oil and gas wells and “land uses in support of” wastewater injection in unincorporated areas of Monterey County were enacted as part of Measure Z, an initiative sponsored by PMC and passed by Monterey County voters.The trial court upheld, in part, a challenge to Measure Z by oil companies and other mineral rights holders. The court of appeal affirmed. Components of Measure Z are preempted by state laws. Public Resources Code section 3106 explicitly provides that the State of California’s oil and gas supervisor has the authority to decide whether to permit an oil and gas drilling operation to drill a new well or to utilize wastewater injection in its operations. Those operational aspects of oil drilling operations are committed by section 3106 to the state’s discretion and local regulation of these aspects would conflict with section 3106. View "Chevron U.S.A., Inc. v. County of Monterey" on Justia Law

by
Plaintiff Margaret McCann appealed a judgment in favor of defendant City of San Diego (City) on McCann’s petition for writ of mandate and an order denying her request for a preliminary injunction. McCann challenged the City’s environmental review process related to its decision to approve two sets of projects that would convert overhead utility wires to an underground system in several neighborhoods. McCann’s primary concern was the need for the underground system to be supplemented with several above-ground transformers, which would be housed in three-foot-tall metal boxes in the public right-of-way. According to McCann, the City violated the California Environmental Quality Act (CEQA) by failing to prepare an environmental impact report (EIR) for both sets of projects. The Court of Appeal concluded McCann’s claims were barred as to the first set of projects because she failed to exhaust her administrative remedies to challenge the City’s determination that the projects were exempt from CEQA. The Court determined the City complied with the CEQA. However, the Court found merit in McCann’s argument the City’s finding that the projects would not have a significant environmental impact due to greenhouse gas emissions was not supported by substantial evidence. The Court found remand was necessary to allow the City to conduct a further review to determine if the greenhouse gas emissions were consistent with the City’s Climate Action Plan. Judgment was therefore reverse in part and affirmed in all other respects. View "McCann v. City of San Diego" on Justia Law

by
In 2016, Placer County, California (the County) approved a project to develop a resort on about 94 acres near Lake Tahoe. Sierra Watch challenged the County’s approval in two lawsuits, both of which were appealed. In this case, Sierra Watch challenged the County’s environmental review for the project under the California Environmental Quality Act (CEQA). In particular, Sierra Watch contended the County: (1) failed to sufficiently consider Lake Tahoe in its analysis; (2) insufficiently evaluated the project’s impacts on fire evacuation plans for the region; (3) inadequately evaluated and mitigated the project’s noise impacts; (4) failed to allow for sufficient public review of the project’s climate change impacts; (5) failed to consider appropriate mitigation for the project’s climate change impacts; (6) overlooked feasible mitigation options for the project’s traffic impacts; and (7) wrongly relied on deferred mitigation to address the project’s impacts on regional transit. The trial court rejected all Sierra Watch’s arguments. But because the Court of Appeal found some of Sierra Watch’s claims had merit, judgment was reversed. View "Sierra Watch v. County of Placer" on Justia Law

by
Three appeals against respondent Department of Water Resources all involved litigation related to changes in long-term water supply contracts brought about by the “Monterey Agreement” and “Monterey Amendment.” In the first case, Central Delta Water Agency, et al. (collectively, Central Delta) appealed the trial court’s decision on a petition for writ of mandate challenging the adequacy of the “Monterey Plus” environmental impact report (Monterey Plus EIR) issued in 2010 and the validity of the Monterey Amendment. In the second, Center for Biological Diversity (Biological Diversity) appealed the trial court’s denial of attorney fees incurred in connection with its writ petition against DWR involving the Monterey Plus EIR and Monterey Amendment. In the third case, Center for Food Safety, et al. (collectively, Food Safety) appealed the trial court’s denial of a petition for writ of mandate challenging DWR’s revised environmental impact report on the Monterey Plus project (Revised EIR). Finding no reversible error in any of the three cases, the Court of Appeal affirmed. View "Central Delta Water Agency v. Dept. of Water Resources" on Justia Law

by
The Department regulates the use of pesticides, including 1,3-Dichloropropene (1,3-D), which is used in agriculture. Only Dow produces 1,3-D for use in California As a condition of Dow’s continued registration of 1,3-D products, the Department maintains a “township cap program,” which limits the amount of the pesticide that may be used each year to reduce cancer risks to bystanders. Plaintiffs filed a petition for a writ of mandate, claiming that the township cap program was an underground regulation in violation of the Administrative Procedure Act and fails to incorporate recommendations from the California Office of Environmental Health Hazard Assessment as required under the Food and Agriculture Code.The trial court granted summary judgment, declaring the township cap program void and directing the Department to engage in formal rulemaking to replace it. The court of appeal affirmed, agreeing that the program is an underground regulation. A regulation subject to the APA may exist even if the agency never promulgates a written policy setting forth the rule. The fact that Dow happens to be the only registrant of 1,3-D does not mean the Department can informally regulate the pesticide at will while its rules are implemented as conditions of Dow’s registration; the township cap program is a rule of general application. The program governs how 1,3-D will be used, not how the Department will register pesticides, and clearly implements and makes specific the law the Department administers. View "Vasquez v. Department of Pesticide Regulation" on Justia Law

by
Objectors challenged the Watershed Conservation Authority's (WCA) certification of the environmental impact report (EIR) for a project in the Angeles National Forest (California Environmental Quality Act (CEQA), Pub. Resources Code, 21000). The Project comprises 198 acres along 2.5-miles of the East Fork of the San Gabriel River and will involve the development of new picnic areas, pedestrian trails, river access points and upgrades to existing facilities; improvements to roadways, parking, restrooms, and refuse disposal; restoration of riparian and upland vegetation communities; and implementation of a Forest Closure Order to prohibit overnight camping. The EIR addressed the usual range of potential impacts on the environment, on biological resources, cultural resources, water quality, air quality, and more.The trial court rejected claims that CEQA required WCA to consider additional project alternatives, and that the project was inconsistent with applicable land use plans, but issued a writ of mandate requiring WCA to “articulat[e] and substantiat[e] an adequate parking baseline” for the project, and to reassess the significance of the impacts resulting from the parking reduction. The court later awarded plaintiff attorney fees. The court of appeal reversed as to the parking issue and attorneys’ fees. The trial court erred in its analysis of the parking issue and should have denied the petition in its entirety. View "Save our Access San Gabriel Mountains v. Watershed Conservation Authority" on Justia Law

by
The County appeals from a judgment and issuance of a peremptory writ of mandate in a proceeding under the California Environmental Quality Act (CEQA).In the published portion of the opinion, the Court of Appeal addressed the exhaustion of administrative remedies and the interpretation of the existing facilities exemption. The court concluded that the issue exhaustion requirement does not apply to challenges to the exemptions because the county did not provide adequate notice that CEQA exemptions would be considered at the public hearing held by its Board of Supervisors. Consequently, the county did not provide an opportunity for members of the public to raise objections to its reliance on those exemptions. The court resolved the ambiguity by interpreting the word "facilities" to exclude unlined landfills and therefore concluded that the county misinterpreted the Guidelines and violated CEQA when it concluded the existing facilities exemption applied to the project. The court affirmed the judgment. View "Los Angeles Department of Water and Power v. County of Inyo" on Justia Law